State Senator Mary Lazich (R-New Berlin) represents parts of four counties: Milwaukee, Waukesha, Racine, and Walworth. Her Senate District 28 includes New Berlin, Franklin, Greendale, Hales Corners, Muskego, Waterford, Big Bend, the town of Vernon and parts of Greenfield, East Troy, and Mukwonago. Senator Lazich has been in the Legislature for more than a decade. She considers herself a tireless crusader for lower taxes, reduced spending and smaller government.
I-94 NORTH-SOUTH update: July 18- July 26
Here is an update from the Wisconsin Department of Transportation (DOT) for the I-94 NORTH-SOUTH freeway project:
Construction update July 18 –July 26:
I-94 North-South Freeway Project update for
All closures are weather-dependent and subject to change.
New long-term closures are BOLD.
Saturday, JULY 18
I-94 EAST (SB)
Sunday, JULY 19
I-94 EAST (SB)
Monday, JULY 20
I-894 EB Double Lane Closure at
I-94 WEST (NB) and I-94 EAST (SB) Double Lane
I-94 EAST (SB)
Tuesday, JULY 21
I-894/I-43 EB Double Lane Closure between 35th and 20th Street 9:30 pm – 5:30 am
I-94 WEST (NB) and I-94 EAST (SB) Double Lane
I-94 WEST (NB)
Wednesday, JULY 22
I-894 WB Double Lane Closure at
I-94 WEST (NB) and I-94 EAST (SB) Double Lane
Thursday, JULY 23
I-94 EAST (SB) exit ramp to the Airport Spur Closed 9:30 pm - 4:30 am
I-894 WB Double Lane Closure at
I-94 WEST (NB) and I-94 EAST (SB)
Friday, JULY 24
I-894 WB Double Lane Closure at
Saturday, JULY 25
Only long term closures in effect.
Sunday, JULY 26
Only long term closures in effect.
LONG TERM CLOSURES IN
- Full closure of the
- I-894/43/I-43 WB exit ramp to 27th Street until Mid August
- 27th St entrance ramp to I-894/43/I-43 EB until Mid August
- 27th St NB entrance loop ramp to I-894/43 WB until Mid August
- I-894/43/I-43 WB right lane closure between Mitchell Interchange and 27th St until Mid August
- Single lane closures on NB and SB 27th St between Layton Ave. and Bottsford Ave; both directions of traffic will travel on the 27th St SB bridge over I-894/43 (two lanes in each direction) until Late July
-27th Street NB right lane closure (only one lane open NB) between Layton Ave. and I-894/I-43 7/10 – 7/24
- College Ave from 15th St. to 20th St until November
- I-94 EAST (SB) and WEST (NB) entrance and exit ramps at College Ave closed until November
- Southwest park and ride lot at College Ave closed until November
- Northeast park and ride lot at College Ave closed until late August (Temporary lot available at MATC-Oak Creek campus)
Saturday, JULY 18
Only long term closures in effect.
Sunday, JULY 19
I-94 EAST (SB)
Monday, JULY 20
I-94 EAST (SB) exit/entrance ramps at WIS 165 long-term closures reopen at 12:01 am
I-94 EAST (SB) exit/entrance ramps at
I-94 WEST (NB)
I-94 EAST (SB)
Tuesday, JULY 21
I-94 WEST (NB)
I-94 WEST (NB)
I-94 EAST (SB)
Wednesday, JULY 22
I-94 WEST (NB)
Thursday, JULY 23
I-94 WEST (NB)
Friday, JULY 24
I-94 WEST (NB)
Saturday, JULY 25
Only long term closures in effect.
Sunday, JULY 26
I-94 WEST (NB) exit and entrance ramps at
LONG TERM
- East Frontage Rd
- I-94 EAST (SB) entrance and exit ramps at WIS 158 until Fall ‘09
-
-
-
- I-94 EAST (SB) and WEST (NB) entrance and exit ramps at
-
- Single lane closure I-94 WEST (NB)
- Single Lane Closure I-94 EAST (SB)
- CTH G full closure between freeway ramps and east of
- Single Lane Closure I-94 EAST (SB) at
- I-94 WEST (NB) exit and entrance ramps at
- East Frontage Road at
-
-
-
This site uses Facebook comments to make it easier for you to contribute. If you see a comment you would like to flag for spam or abuse, click the "x" in the upper right of it. By posting, you agree to our Terms of Use.